Brentwood Micromanaging of Fire Station Design Could Cost Taxpayers Additional $500k

Contra Costa County Fire confirmed that the cost of Station 94 in the City of Brentwood could increase by more than $500k.

The current cost estimated is around $13 million and the increase comes after micromanaging of the design by the Brentwood City Council and Brentwood Planning Commission who expressed concerns over the design, brick color, and windows. A design was originally presented by the fire district, with the assistance of city staff, within the downtown specific plan, but the planning commission suggested staff was wrong and denied the project (design review) in a 4-0 vote for various reasons–including suggesting another location would be better.

In June, after Brentwood Councilmember Tony Oerlemans pulled the vote for council review, the fire station was approved, thus overturning a planning commission vote, by the Brentwood City Council in a 3-2 vote with Mayor Susannah Meyer and Councilmember Jovita Mendoza dissenting.

With the delays from the planning commission and ultimate approval, and required changes requested by the city council, it added costs to the fire station construction. Deputy Fire Chief Aaron McAlister confirmed the cost increases will be coming:

“Yes, $500K is an estimate I have been using in various venues.  This actual number is still becoming clear.  Many of the changes touch multiple design subs and multiple construction trades.  Here are a few things that go into that estimate:

    • Architectural fees- redesign, additional meeting attendance
    • Structural Engineers- redesign, windows with cornices (front and rear), parapet roof line changes
    • Civil Engineers- add trees, delete parking stall in rear lot
    • Landscape Designers- add trees to the rear lot, irrigation changes 
    • General Construction- change from bid price for actual construction costs for both materials and labor-TBA,  
    • General delay costs due to delayed approval- extended general conditions for the project team and delayed mobilization

We are happy with the new design and like the look. Bottom line is it comes with a cost to the Fire District.  All projects have change orders, and it’s part of the process.”

The final costs will not be known until completion of the fire station which is estimated in 2026.

On September 8, they held a groundbreaking for the station which is located 739 First St. It replaces the original station that was demolished in 2022. The new station is a new 8,137 square foot, two-story fire station, including two apparatus bays, living areas, and associated site improvements, on a 13,427 square foot parcel. The apparatus bays will house a Type I engine and Type III engine, but no ladder trucks. Fire engines would only enter the site from Diablo Way, along the rear property line, and exit onto First Street. Pedestrian access would be from First Street.


Previous

Related posts

Contra Costa Supervisors Could Issue Subpoenas to County Assessor Over Financial Audit

Brentwood Appoints Christopher Lazaro as Deputy City Manager

Brentwood: Liberty High School Hit With Bomb Threat